Moderating Role of Stakeholders Attributes on Implementation of Rural Electrification Projects in Kenya

Authors

  • Enock Kiage Nyaboga

  • Prof. Iravo Mike Amuhaya

  • Dr. Muchelule Yusuf Wanjala

Keywords:

project risk management; project planning; project leadership,

Abstract

Stakeholders strongly influence the outcome of projects especially in complex projects with heterogeneous stakeholders, thus understanding their influence is essential to ensure project success and attainment of objectives. The benefits of rural electrification range from lighting, access to information, improved study environment for school children as well as improved businesses which in turn create employment opportunities and contribute to development and poverty reduction. This study sought to examine the role of stakeholders in the implementation of rural electrification projects in Kenya. The study focused on project risk management, planning, leadership, monitoring, and control roles with a moderating role of stakeholders' attributes in the implementation of rural electrification projects in Kenya. The research targeted rural electrification projects implemented by the Kenya government in public primary school. The key respondents of the study were project managers of all the implemented projects.

How to Cite

Moderating Role of Stakeholders Attributes on Implementation of Rural Electrification Projects in Kenya. (2020). Global Journal of Management and Business Research, 20(46), 55-71. https://journalofbusiness.org/index.php/GJMBR/article/view/3284

URL: https://journalofbusiness.org/index.php/GJMBR/article/view/3284

References

K. Aaltonen (2010) Stakeholder Management in International Projects.

M. Affare (2012) An assessment of Project Communication Management on Construction Projects in Ghana.

H. Albert (2004) Part 3: Project management procedures. 31-364.

Vittal Anantatmula (2010) Project Manager Leadership Role in Improving Project Performance. 22(1), 13-22. https://doi.org/10.1080/10429247.2010.11431849

Lynda Bourne, Derek Walker (2006) Visualizing Stakeholder Influence - Two Australian Examples. 37(1), 5-21. https://doi.org/10.1177/875697280603700102

A. Ceric (2003) A Framework for Process-Driven Risk Management in Construction Projects.

Y. Chang (2013) Performance measurement and adoption of balanced scorecards: a survey of municipal governments in the USA and Canada.

D. Cleland (2006) Project management: Strategic design and implementation (5th ed.).

D. Cleland (1986) Project Stakeholder Management. 17(4), 36-44.

D. Cooper, P. Schindler (2011) Business research methods, (11th. 20.

COSO (2004) Enterprise risk management - Integrated framework, executive summary, framework.

J. Creswell (2012) Research Design: Qualitative, Quantitative, and Mixed Methods.

Deloitte (2013) GCC Powers of Construction 2013.

K. Donald, L. Delno (2006) Proposal and Thesis Writing; An Introduction.

Thomas Donaldson, Lee Preston (2009) The Stakeholder Theory of the Corporation: Concepts, Evidence, and Implications. 20(1), 65. https://doi.org/10.2307/258887

Dov Dvir, Tzvi Raz, Aaron Shenhar (2003) An empirical analysis of the relationship between project planning and project success. 21(2), 89-95. https://doi.org/10.1016/s0263-7863(02)00012-1

Dov Dvir, Arik Sadeh, Ayala Malach-Pines (2006) Projects and Project Managers: The Relationship between Project Managers' Personality, Project Types, and Project Success. 37(5), 36-48. https://doi.org/10.1177/875697280603700505

G. Flanagan, U. Norman (2003) Assessment and Control of Project Risks.

J. Fraenkel, N. Wallen (2002) How to design and evaluate research in education (5th ed.).

R. Freeman (2015) A Stakeholder Theory of the Modern Corporation. 112-122.

B. Hebert (2002) Tracking progress: More companies are recognizing the value of project management as part of their overall strategy particularly in times of change. 24-27.

C. Jäger (2008) The Principal-Agent-Theory within the Context of Economic Sciences.

Kam Jugdev, Ralf Müller (2005) A Retrospective look at our Evolving Understanding of Project Success. 36(4), 19-31. https://doi.org/10.1177/875697280503600403

J. Kariuki (2015) Project manager's leadership style, teamwork, project characteristics, and their.

A. Keegan, D. Hartog (2004) Transformational leadership in a project-based environment: a comparative study of the leadership styles of project managers and line managers. 22(8), 609-617. https://doi.org/10.1016/j.ijproman.2004.05.005

H. Kezner (2009) Project Management - A Systems Approach to Planning,Scheduling,and Controlling.

Grant Kululanga, Witness Kuotcha (2010) Measuring Project Risk Management Process for Construction Contractors with Statement Indicators Linked to Numerical Scores", Engineering. 17(4), 336-351. https://doi.org/10.1108/09699981011056556

Kedsuda Limsila, Stephen Ogunlana (2008) Performance and leadership outcome correlates of leadership styles and subordinate commitment. Engineering. 15(2), 164-184. https://doi.org/10.1108/09699980810852682

T. Lucas (2009) Quantifying complexity.

B. Maina (2013) Influence of stakeholders' participation in the success of the economic stimulus program: a case of education projects in Nakuru County, Kenya.

Chiku Malunga, C. Banda (2004) Understanding Organizational Sustainability through African Proverbs. https://doi.org/10.3362/9781780447599

H. Maylor (2010) Project management (4th ed.).

R. Miller, D. Hobbs (2005) Understanding and managing risks in large engineering projects. 19(8), 437-443. https://doi.org/10.1016/s0263-7863(01)00045-x

Ronald Mitchell, Bradley Agle, Donna Wood (1997) Toward a Theory of Stakeholder Identification and Salience: Defining the Principle of Who and What Really Counts. 22(4), 853. https://doi.org/10.2307/259247

O. Mugenda, A. Mugenda (2013) Research methods. Quantitative and Qualitative Approaches.

R. Müller, K. Jugdev (2012) Critical Success Factors in Projects: Pinto, Slevin, and Prescott - the elucidation of project success. 5(4), 757-775.

R. Muller, Turner (2007) Matching the project manager's leadership style to project type. 25(1), 21-32. https://doi.org/10.1016/j.ijproman.2006.04.003

Brian Nocco, René Stulz (2006) Enterprise Risk Management: Theory and Practice. 18(4), 8-20. https://doi.org/10.1111/j.1745-6622.2006.00106.x

N. Ongegu (2010) The Challenges faced by Kenya Power and Lighting Company in the Implementation of Change Program of The Energy Sector Recovery Project.

J. Pinto (2010) Project management: achieving competitive advantage.

PMI (2014) A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 9073-3299.

M. Porter, M. Kramer (2006) Strategy and society: the link between competitive advantage and corporate social responsibility. 84(12), 78-92.

K. Remington, R. Zolin (2011) Controlling Chaos? The Value of the Challenges of applying. In L. C. T. Cooke-Davies. 115-128.

M. Saunders, P. Lewis, A. Thornhill (2007) Research methods for business students, (4th Ed.).

Martin Schieg (2008) STRATEGIES FOR AVOIDING ASYMMETRIC INFORMATION IN CONSTRUCTION PROJECT MANAGEMENT. 9(1), 47-51. https://doi.org/10.3846/1611-1699.2008.9.47-51

U. Sekeran, R. Bougies (2010) Research Methods for Business: A skill-building Approach (5th ed.).

S. Shapiro, M. Wilk (1965) An Analysis of Variance Test for Normality (Complete Samples). 52(3/4), 591. https://doi.org/10.2307/2333709

Aaron Shenhar, Dov Dvir, Ofer Levy, Alan Maltz (2001) Project Success: A Multidimensional Strategic Concept. 34(6), 699-725. https://doi.org/10.1016/s0024-6301(01)00097-8

H. Sherman, S. Ralph (1998) Open Boundaries: Creating Business Innovation Through.

J. Turner, Ralf Müller (2004) Communication and Co-operation on Projects Between the Project Owner As Principal and the Project Manager as Agent. 22(3), 327-336. https://doi.org/10.1016/j.emj.2004.04.010

R. Turner, R. Muller (2005) The Project Manager's Leadership Style as a Success Factor on Projects: A Literature Review. 36(2), 49-61. https://doi.org/10.1177/875697280503600206

M. Vanek, Y. Toma Škova, A. Strakova, K. Špakovska, P. Bora (2013) Risk assessment mining related project management. (3), 47-53.

Rebecca Yang (2014) An investigation of stakeholder analysis in urban development projects: Empirical or rationalistic perspectives. 32(5), 838-849. https://doi.org/10.1016/j.ijproman.2013.10.011

A. Zakharova, T. Jäger (2013) Stakeholder Participation to improve Societal acceptance for Mega Projects: A case study of the forum for the coal-power.

Moderating Role of Stakeholders Attributes on Implementation of Rural Electrification Projects in Kenya

Published

2020-11-11

How to Cite

Moderating Role of Stakeholders Attributes on Implementation of Rural Electrification Projects in Kenya. (2020). Global Journal of Management and Business Research, 20(46), 55-71. https://journalofbusiness.org/index.php/GJMBR/article/view/3284